The project: current status
Roles
Project owner: the municipality; it is the entity that issues the calls for tenders.
Step 1: Call for tenders – Assessment Step 2: Call for tenders – Project ownership Step 3: Call for tenders – Project management/execution
This is the first step in the restoration project. The assessment was carried out by heritage architects and accredited restorers in June 2023.
Step 2: Call for tenders – Project ownership
The key players are heritage architects. A study is being conducted to define the scope and timeline of the restoration project. The project is slated for completion in 2025.
Step 3: Call for tenders – Project management/execution
The choice of companies that will operate the catering will be made in 2026.
The church is open daily from 10:00 AM to 6:00 PM:
•





Initiative
The association was founded at the initiative of its president, Alain D'haene, who was immediately joined by local residents and people from the surrounding area. Building on this momentum, the municipality of Cazeaux decided in February 2021 to contact the DRAC (Regional Directorate of Cultural Affairs) to explore the restoration and showcasing of these paintings.
Action Taken
Mr. Denis Dodeman, Chief Architect for the Hautes-Pyrénées, and the restoration firm Atelier 32 were selected to conduct the diagnostic study, which was submitted in June 2023. Our association helped the municipality fund 20% of the study, covering 50% of the remaining cost to be borne by the local authority. Subsequently, heritage architects Pascal Robert-Cols and Olivier Prax conducted a study to draw up the preliminary project design, proposed for 2025; this includes an initial phase of work focusing on the roof structure, a complete roof replacement, and masonry remediation on the north side. A call for tenders was launched to select the contractors. Funding applications resulted in the awarding of grants. The first phase has been approved and is being subsidized by the DRAC, the Haute-Garonne Departmental Council, and the Occitanie Region. Contracts are to be signed in the first quarter of 2026, with work beginning this summer. The grants have been secured, and the project is supported by the Heritage Foundation (Fondation du Patrimoine).
Work Remaining
The optional phase, covering the bell tower, electrical systems, lighting, and stained-glass windows. The contractors have been selected, but this second phase will only begin once the first has been completed. Funding applications have not yet been prepared.
Local partners
The town halls of Oô, Saint-Aventin, Sode, and Salles-et-Pratviel, and, of course, the town hall of Cazeaux-de-Larboust.


Institutional partners
DRAC
Haute-Garonne Departmental Council
Occitanie Region
Heritage Foundation